Expect more construction on LSU campus as officials move forward with lighting improvements

Expect more construction on LSU campus as officials move forward with lighting improvements
Bank Image

BATON ROUGE, La. (BRPROUD) – LSU leaders continue to make campus safety a priority by moving forward with a Lighting Improvement Plan that’s been in the works for more than five years.

According to a Wednesday, May 17 update from the university, construction work aimed at improving lighting across the campus will be accelerated in the next 12-18 months. Efforts will be sped up thanks to state funding and LSU’s investments, officials said.

LSU based its decisions on where to improve lighting after considering multiple factors. For one, they conducted a lighting survey in April 2020. The survey involved the use of a light meter, which is a highly sensitive piece of equipment designed to measure the amount of light either falling on a surface or reflected from a surface. Officials used the meter to collect light-level data across the entire campus. Every second, light levels were read and linked to a GPS log that showed the location of each measurement. This survey information was then analyzed in conjunction with two factors, the LSU Police Department’s data on crime hotspots and input from the student government’s annual Light Walk.

After using the data above to figure out where lighting improvements were necessary, officials planned to carry out the upgrades in three phases, with two additional anticipated projects.

The projects are currently underway. As upgrades are made, temporary lighting has been set up in a number of key areas across campus. These include the Parade Ground and various student parking lots.

Just below is a general overview of the project’s phases.

Phase One

Impacted Area(s): The parking area across from Patrick Taylor Hall, which is known as Touchdown Village, and the Ag/Coliseum parking areas.

Construction Dates: October 3, 2022 – February 10, 2023

Status: Completed

Project Type: State Project

Additional Notes: None


Phase Two

Impacted Area (s): The Law School, Campus Lake, Highland Road, the Quad, and the pedestrian corridors around Coates Hall, the Renewable Natural Resources Building and Sturgis Hall.

Construction Dates: February 27, 2023 – November 4, 2023

Status: In Progress

Project Type: State Project

Additional Notes: Lighting near the Law School and Campus Lake were prioritized. After these areas were upgraded, officials shifted their focus to improving the lighting around Highland Road, the Quad, and the pedestrian corridors around Coates Hall, the Renewable Natural Resources Building and Sturgis Hall.


Phase Three

Impacted Area(s): The pedestrian corridors around the Pentagon Residential Community and the LSU Campus Mounds, areas along North Stadium Road, and parking lots along South Stadium Road and Skip Bertman Drive.

Construction Dates: May 2023 – February 2024.

Status: In Progress

Project Type: State Project

Additional Notes: Bids made on Phase 2 were significantly lower than officials expected. For this reason, a Phase 3 project was added to allow for additional lighting upgrades to be carried out with the assistance of state funding.


Enchanted Forest Lighting Project

Impacted Area(s): The wooded area between the Greek Theater, Pentagon dorms and Kirby Smith parking lot, which is known as the “Enchanted Forest.”

Construction Dates: June 2023 – December 2023

Status: Planning Stages

Project Type: LSU Project

Additional Information: This LSU-funded, LSU-contracted project is expected to be completed with the assistance of approximately $500,000 in Enhancing the Core funds.


Additional Lighting Projects

Impacted Area(s): To Be Determined

Construction Dates: Undetermined

Status: In Progress

Project Type: LSU Project

Additional Information: Remaining funds from Enhancing the Core might be used to ensure all Phase 3 State Project priorities are met. However, if state funding is able to cover the costs associated with Phase 3, then LSU will identify additional lighting priority zones for the remaining Enhancing the Core funds.

Source

About Mary Weyand 13343 Articles
Mary founded Scoop Tour with an aim to bring relevant and unaltered news to the general public with a specific view point for each story catered by the team. She is a proficient journalist who holds a reputable portfolio with proficiency in content analysis and research. With ample knowledge about the Automobile industry, she also contributes her knowledge for the Automobile section of the website.

Be the first to comment

Leave a Reply

Your email address will not be published.


*